2016年3月21日星期一

Chain Jump Treatment of Buried Chain Scraper Conveyor

When buried scraper conveyor chain jumping failure occurs, it is rarely happens that the chains of both sides are out of sprocket. Generally, single side chain sprockets meshing point will cause both sides chain dislocation and lead the scraper chain in the tilt state of operation. At this moment, stop and repair the machine in time will bring it back to normal running. However, if the failure is not found promptly, more and more serious dislocation could cause chain breaking, cast stone runnel box or chain way damage, and even burn the motor and turn over the base, thus extend the harm of jump chain failure.
The most common issue in the operation of buried scraper conveyor is chain jump and often occurs at the head and tail. While the causes are complicated, such as uneven lining slot box, partly cast slab laying off, gaps at chain way and some other reasons. After long time running, the head gear tooth and tail groove wear is also a factor causing this problem. In addition, when the large bulk materials are conveying, they might enter into the sprocket meshing point which can also cause chain jump.


2016年3月18日星期五

Feeding Material in Proper Order of Buried Scraper Conveyor

Equipment failure happens when improper operation made in the running process of buried chain scraper conveyor. Please pay attention to the the material feeding sequence.
During material conveying, turning on the device at the first place and opening feed inlet afterwards. In this case, scraper conveyor would not be filled with material avoiding unnecessary losses because of overload motor. When material conveying finished, turn off the slide damperor or the power of the discharger firstly, stop material feeding and turnoff squeegee machine after clean up the material in the conveyor chamber. It will prevent the material accumulation in the equipment avoiding material moisture and agglomeration.
If you want know more about us, please click here:http://www.pkmanufacture.com

2016年2月27日星期六

How to Resolve Chain Deviation of Buried Scraper Conveyor

1. Check installation quality and take measures to correct mounting dimensions.

1) Check and adjust the flange connections between conveyor casings, make sure the connections are smooth and tightly sealed. 

2) Adjust the clearance between chain and conveyor trough. The appropriate clearance value will guarantee the conveyor to operate normally, reduce energy consumption, extend the service life of chain scraper & conveyor trough, and improve transport efficiency. 

3) Check and adjust the surface flatness of guide rail. The joints between guide rails should be smooth.

4) Check and adjust head and tail pulleys, which should be on one center line and correct meshing.

5) Correct and replace the deformed scrapers.

6) Repair and replace the worn-out guide rails.

7) Adjust the tension device, make sure the elastic of chain & scraper is moderate, and the tensile force of left and right sides are the same. 

2. Adjust material drop point.
Material impact is one of important factors that cause chain deviation. The solution is to install a retaining plate at the inlet. In this case, the material will fall in the middle position of scraper & chain to make sure the chain will be uniformly forced, so as to reduce chain deviation. 

3. Install baffle plates on both sides of the chains to prevent deviation phenomenon. 

2016年2月2日星期二

Difference between forging and casting of scraper chain machining process

Forging and casting is commonly used in the mechanical processing of scraper chain, but do you know the differences? Today, PK Machinery will introduce it in details.
Forging is a processing method which uses the forging machinery occurs pressure to metal blank, make it produce plastic deformation to obtain a certain mechanical properties, a certain shape and dimension.
Casting is the process thatmakes the metal melt into a certain requirements of liquid and pour into the mold, after cooling, solidification, and cleaning the whole process to obtainwith a predetermined shape, size and performance of the casting (parts or blanks).
Generally forging chain mechanical properties are generally better than the same kind of casting chain, but the cost is higher. Although the cost of casting is low, but the production needs more materials and equipment, it will produce dust, harmful gases and noise which will pollute the environment, so we will choose forging chain as the traction component of scraper conveyor in most cases.

2016年1月12日星期二

How to Choose the Scraper and Chain of Buried Scraper Conveyor? (II)

1. Selection of  Scraper Conveyors Chain
On the basis of meeting the adaptability to material, the chain should be selected reasonably according to maximum working load.
1) Bush roller chain should not be used for dust conveying, and should be first selected to transport the material which is easy to float chain. But in general, die forging chain is used as the first choose.
2) Base on the assurance of maximum chain working load, in order to maximize its carrying capacity,
it is best to use the chains which allowable load is close to maximum working load.
3) On the condition of meeting strength requirement, it should be try to reduce chain weight.
4) Different kinds of chains are used for different arrangement form.
MS / MC / MG buried scraper conveyors: three types of chains can be used, bush roller chain, die forging chain and double chain.
MZ / MP buried scraper conveyors: die forging chain
MK / ML buried scraper conveyors: die forging chain and double chain
2. Selection of Chain Pitch
The selection principle is to minimize the maximum dynamical load and up & down movement speed of chains. If the chain shake is too big, it will destroy normal material transportation, especially vertical conveying. And big dynamical load will lead to the increase of chain weight or decrease of its service life. 
3. Selection of Scraper Pitch
The scraper pitch can be determined according to the conveyor trough width, but it must be adaptable to chain pitch. If the scraper pitch is too big, it can lead to relative slippage between various material layers in conveyor trough, so as to increase energy consumption and even destroy normal material transportation. On the contrary, too small scraper pitch will increase the traction weight and energy consumption. 
The scraper pitch generally equals to chain pitch. When the load is small, the scraper pitch can be chosen the twice of chain pitch. Meanwhile the material features should be taken into consideration, for example, when conveying viscous material, the manufacturer can install a special form scraper, to remove the sticking of material inside conveyor trough, and prevent most viscous material bonded on the inner wall of conveyor trough.


2016年1月8日星期五

Long life chain trough scraper conveyor

1. Scraper chain conveyor should be no-load running for a certain time when start the equipment every time, Then feed the material after the equipment working normally. We should keep feeding the material evenly, sudden feeding or over-load running is not allowed.
2. Should not stop the machine with load if there is no special condition.
Generally,we should stop the equipment when the material in the trough were discharged completely after we stop feeding the material.
3. If the whole production line is consist of sets of conveyor, we should
start the last set first when start the whole system, then start the others one by one . The order will be opposite when stops.
4. Operators should check the spare parts of the conveyor timely, especially the conveyor chain and driven device.
5. During operating, we should protect the conveyor from the iron, large hard objects and impurities to avoid damage the equipment.
6. Should keep all the bearing and driven device lubricated well. However, should not lubricate the conveyor chain, support guide rail, head wheel and tail wheel etc.
7. In general, the buried scraper conveyor should be minor repair every half year, medium repair every year and overhaul every three years. For overhaul the buried scraper conveyor, we should remove and clean all the spare part, replace all the wear part. For the motor and reducer, should be maintained and repaired according to their technical requirement.